|
|
|
| Sediment
Problems of Irrigation Canals: Field Studies to Assess the Changes in
Canals Profiles and Cross Sections Dr. Taha Mohammed Tahir Dr. Eng Abdulla Abdulkader Noman |
Abstract Wadi Zabid is one of the main agricultural Wadis in the Tihama Plain. Wide ranges of crops have been cultivated such as cereals, vegetables, fruits, and some cash crops like cotton, sesame and tobacco. It has provided the country with high valued food basket as well as exporting to the neighboring countries. The government realized the importance of Wadi Zabid and started in 1979 constructing diversion works and canals to maximize the agricultural output of the Wadi. During the past twenty years of operations, sediment deposition in front of the diversion works and along the canal system posed serious threats to the project network. Sediment deposition caused many problems such as blocking the off take pipes and gates, raising canal beds and reducing canals slope, increasing the field levels and reducing canal flow capacity. This study would assess the changes in canal sections and profiles at which the present canal profiles and sections are drawn and compared with the canal profiles and sections of the previous years to provide sound basis for problems assessment. Laboratory experiments and sieve analysis were conducted to analyze canal bed samples in order to draw recent grading curves and compared it with the previous grading curves of the canals. This study exposed the fact that canal sections and profiles are changed greatly due to the accumulation of sediments in the upper reaches of the canals whilst equilibrium sections and profiles existed in the middle parts with section erosion in the lower parts of the canal reaches. It also indicated that greater sediments sizes were deposited in the canal upper reaches, which meant that canal behavior is changed and does not work as it was designed for. Key words: Sediments, Irrigation Canals, Profile, and Cross-section 1. Introduction 1.1 General Description of the Study Area Yemen Republic is located in the southwestern corner
of the Arabian Peninsula (figure 1.1). In the western part of Yemen
is the Tihama coastal plain, bordered to the west by the Red Sea and
to the east by the mountains. The Tihama plain is a semi-arid coastal
plain, which is 25- 45 km wide. The total cultivated land is about 500,000
ha which is used to produce various cereal, vegetable and different
crops. More than 30% of the Tihama plain consists of alluvial fans,
crossed by seven major Wadis originating from the mountains in the east
as shown in figure (1.1). These seven Wadis have steep bed slopes of
0.5 to 100 and their flows are characterized by series of multi-peak
flash floods (spates). The water flows in a series of multi-peak flash
floods. Settlement in the Tihama plain has been dependent on flood-spreading techniques of Wadi flows for irrigation, which have been developed over many years. In order to make best use of the agricultural potential of the Tihama plain, the Ministry of Agricultural and Water Resources planned a single-wadi development strategy, starting from the three major wadis; Zabid, Rima and Mawr. Major irrigation development projects have been completed in the three wadis (Zabid (1979), Mawr (1984) and Rima (1988)). 1.1.1 Wadi Zabid Wadi Zabid is the second major Wadi after Wadi Mawr in the Tihama plain (see table 1.1). Wadi Zabid runs east west direction from the foothills of Ibb Governorate with a total length of 250 km. It contains one of the oldest and most highly developed traditional spate systems in the Tihama plain and was the first area given funding for development. Wadi Zabid's climate is generally described as tropical
with a rainy summer and dry winter. The annual rainfall varies from
100 mm near the Red Sea coast to 600 mm in the foothills. The annual
rainfall in the catchments area of the Wadi ranges from 400 to 600 mm/yr,
which increases in some years up to 1000 mm [2]. Wadi Zabid traditional irrigation system consists of 16 main supply canals, which divert flash floods and base flow from the Wadi to the fields by means of deflectors or dykes crossing the Wadi bed. The structures are made from poorly compacted earthen materials (soil, gravel, tree branches and boulders). Hence these structures are often damaged or completely destroyed by medium to large floods [4]. In Zabid area basin irrigation has been practiced for centuries and water was distributed by a field -to-field method. The water rights in the Tihama Wadis declare the priority of higher lying area over lower lying ones in diverting water from the Wadi for irrigation (Al Aala-Fal -Aala), [4]. In the Zabid area special water rights have been formulated approximately 500 years ago. These rights make maximum use of the base flow and periodic floods by means of a time and space relationship based on the experience of centuries. The irrigated areas supplied by the 16 canals were divided into three groups. The timing and frequency of water intake were defined for each group as shown in table (1.2). In 1996 the existing water rights law still recognized [3]. Wadi Zabid irrigation system has 5 diversion structures with 9 head regulators (see figure 1.3) serving 16 canals (see table 1.3), which allow the available spate flows to be allocated in accordance with the traditional water rights [4]. The average quantity of suspended sediment in an average year in Wadi Zabid is about 3,000,000 tons (1,600,000 ) and the bed load is about 430,000 tons (240,000 ) [1]. The sediment concentration especially in the sand size rages rises to more than 10% by weight during large floods [6]. 1.1.2 Existing Problems in the Irrigation System 1.1.2.1 Operation and Maintenance Problems 1.1.2.2 Sediment Problems in the Irrigation Canals The sediment deposition was the main problem in the irrigation system, which was in fact a result of mismanagement of the control structures. The medium and large floods always carried heavy bed and suspended loads, which was deposited when the velocity decreased in the pool until the sediments accumulated up to the weir crest level and then the sediment is deposited in front and behind the intake gates of the head regulator. Then the sediment entered the irrigation canal and is deposited in the head reach and along the canals. This sediment deposition prevented the head regulator to control the Wadi flood flow in a correct way. The sediment deposition caused the following problems 2. Materials and Methods 2.1 Sediment transport studies in the Tihama plain Several sediment transport studies were carried
out in the Tihama wadis as part of the various visibilities / design
studies of the irrigation systems in these wadis such as the following:
- 2.2.1 Longitudinal Profile and Cross-sections Measurements The longitudinal profile was measured to find the bed level elevation at several parts along the canal to estimate the sediment deposition in the canal bed. The profile was measured by leveling equipment (level, staff, etc). The measurements of the profile were taken at the centre of the canal bed and at an interval of 100 m along the canal. During the fieldwork two profiles were measured; one for the Bunny-Barry canal with 2700 m long (see figure 1.3) for the whole profile. The second profile was for the Mawi- Yusifi canal with a total length of 2100 m (see figure 1.4) for the whole profile. The cross-sections were measured to find the elevation and shape of the canal at specific points and at different dates. 2.2.2 Measurements of particle size, discharge, and velocity 2.2.3 Particle size measurements A sufficient large portion (mass) from the sample, which was brought from the field as suspended load, was washed through the sieve no.200 (0.075µm) in order to obtain a mass of 500 g. This mass was placed in the oven at 110 °C for 24 hours to dry. 2.2.3.1 Discharge and velocity measurements The discharge at a given section could be measured by several methods such as: current meter method, float method or dilution method. The choice of the method depended on the conditions present at the site. To facilitate comparison, the sites chosen for discharge measurements were the same as those selected by Lawrence during his 1982-1983 fieldwork. The accuracy of the discharge measurement depended on the number of verticals at which the depth and the velocity were measured. The position of the verticals should be in line with the variation in canal bed elevation and the horizontal variation in velocity. The width between any two verticals should not be more than 1/20 of the total width. The channel width was measured from a fixed reference point (usually the initial point on the bank). A graduated tape determined the distance between verticals and the depth was measured with the graduated metal rod of the current meter. The velocity was measured at one or more points in each vertical. The velocity was then determined by counting the revolutions of the propeller of the meter during 50 seconds at every point. The average velocity was determined by the three-point method, which took the velocity observations in each vertical at 0.2, 0.6, and 0.8 intervals of the total water depth measured from the water surface. The average of the three values gave the mean or average velocity in the vertical. 3. Results And Discussion 3.1 Canals Longitudinal Profiles and Cross Sections The elevation surveys of Bunny-Barry and Mawi-Yusifi canals were done during the fieldwork. From these surveys the bed levels were computed and compared with the designed bed levels (as shown in figures 1.3 and 1.4). A deposition of sediment occurred in all canals reaches, but it was most severe in the head reaches of canals close to the head regulator and at the upper portions of every reach before the drop structure. The deposition at the head reach caused the canal bed level to increase to the extent that water level became higher than that in the upstream of the head regulator. 3.1.1 The Bunny-Barry canal longitudinal profile shows: There was much sediment deposition in the head reach of this canal and little erosion in the downstream reaches (as shown in figure 1.3). The present longitudinal 1996 profile for the downstream reaches appeared lower than the design and other profiles which were measured in the previous years. However, the head reach profiles for the years 1996 and 1983 survey were similar due to a high sediment deposition and the widening of the canal. The following observations can be made: - i. Large sediment deposition in the head reach of the
canal (from 0 to 600 mdownstream the The cross-sections profiles of Bunny-Barry canal showed both the rise in canal bed levels and the reduction in canal width in the downstream reaches. The reduction of canal width in the downstream canal cross-sections was partly due to the natural deposition of sediments in the canal side where the flow velocity is slower. The second reason for reduction of canal width was the disposal of sediment on the canal banks and there back filling into the canal sides. The cross section at the head reaches was enlarged forming a small settling basin immediately downstream of the head regulator. The bed level at section no.1 during the present survey was about 1.0 m above the design full supply level. The accumulation of sediment caused a reduction of both the canal intake capacity and the bed slope near the head regulator. Cross section no.1 (figure 1.5) shows the enlarge section since the 1987 survey, which could be the result of sediment removal from the canal bed to the canal bank. However, there was a reduction in the cross-section area and erosion in the canal bed at the downstream reaches (section. 2, 3 and figures 1.6 and 1.7). The erosion in the canal bed was due to the increase of bed slope and flow velocities, and the sediments clearance before the present measurements 3.1.2 The Mawi-Yusifi canal longitudinal profile shows Substantial depositions of sediments occurred, especially at the head reach near the head regulator (0 to 429 m reach) and after drop structures 1 and 2. The deposition in these reaches was about 1.5 m thick at the upper part, which decreased, in a downstream direction forming a very steep bed slope (as shown in figure1.4). This figure also shows similar but thinner layer of sediment in the (429 to 800 m, 800 to 1580 m and 1580 to 2100 m) reaches. From the longitudinal profile, the sediment deposition height reached about 1.5 m above the canal bed at some places (as shown in figure 1.4). This canal need sediments clearance to prevent the sediment transport of coarse materials through the downstream reaches and finally to the fields. Comparing the existing canal bed slope for each reach
(as determined from the profiles data) with the design or built bed
slopes (see table 1.4), it became clear that the bed slop has increased
with time due to the sedimentation on the canal bed and the erosion
of this bed in some reaches due to the increased bed slopes and flow
velocities. The results in table (1.4) show that the average in the
bed slopes of Bunny-Barry was about 1.6 times the design bed slope except
at the head reach where this increase was about 2.6 times the design
bed slope. Finally, for all canals the most significant impact of sedimentation occurred at the canal head reach, near the head regulator. This sedimentation may reduce the diverted water to the canals especially when the bed level closer to the intake becomes higher than the intake bed level. In this case the sediment had to be removed (mechanically) in order to increase the diverted wafer to the canals and to minimize transporting sediments downstream through the canal an finally to the fields. 3.2 Canal Bed Materials Bed materials samples were collected from various locations along the Bunny-Barry canal and from the Mawi-Yusifi canals. The bed material of Bunny-Barry canal was found to consist of coarse sand and gravel at the head reach (see section 1 of figure 1.8) and coarse to fine sand at the downstream (see sections 2 and 3 of figures 1.9 and 1.10, respectively). The comparison of the grading curves of the Bunny-Barry canal profile observed by Lawrence and the present grading curve from Mawi-Yusifi canal (see figure 1.11), clearly demonstrated that the bed material of the measured curves was a little bit coarser than that mad by Lawrence (1983) (6). This due the following reasons: a. The increase in canal bed slope. The close to the head reach (in the first 100 m) ranges from 30 to 17 mm in size and reduces in the downstream reaches to 0.36 mm. This bed material was a little bit coarser than that observed by Lawrence in 983. The suspended sediments, which enter the fields, cause
elevation of the soil surface, which eventually caused difficulties
in irrigating the fields from the usual off-take. To overcome these
difficulties, farmers usually lay down a temporary earth dykes to pond
the water up to enter the fields. These dykes retained the sediment
behind them and causing canal bed rising Moreover, from the economical point view, the field data indicates that the clearance of sediments from the canals costs 700 YR /ton (5.6 US $/ ton). So the sedimentation of one day will cost about 30,000 YR /day 240 US $/day) for Bunnay-Barry canal and 90,000 YR / day (720 US /dy) for Mawi-Yusifi canal. According to the rate sediment predicted during this study the total costs per season (for 45 days floods) are 1,350,000 YR /year (10,800 Us $ /year) and 4,050,000 YR / year (32,400 U5$/year) respectively. 4. Conclusions and Recommendations 4.1 Conclusions Based on the results and discussion in the preceding sections, the following conclusions can be drawn: 1- The deposition of sediment along the irrigation canals
in Wadi Zabid caused change in canal bed slope and cross section. 4.2 Recommendations In order to improve Wadi Zabid irrigation system
(by reducing the sedimentation problem through the irrigation canals
and minimizing the sediment clearance costs) the following recommendations
are made:
[1] TESCO, " Survey of the Agricultural Potential
of Wadi Zabid in Yemen", Technical Appendix ![]() |
Figure 1.1 Topographical map showsTihama plain and Wadi.

Figure 1.2 Wadi Zabid Irrigation Systems
Figure 1.3: Longitudinal profile of Bunay-Barry cana
Figure 1.4 Mawi-Yyusifi longitudinal profile

Picture (1) sediment deposition in front of the gate
with coarse sediments
Picture (2) Sediment deposition upstream of the weir
increases the bed level of the pool up to
the weir crest
Picture (3) Deposition of sediments U/S of a drop showing
the severe change and increase in the canal bed level.
Picture (4) Complete closure of off take
Table 1.1: Mean annual flow and catchments area of the three
major wadis (after [4])
|
No. |
Name of Wadi |
Catchments area ( |
Annual Flow ( |
|
1 |
Mawr |
8180 |
166 |
|
2 |
Zabid |
4740 |
137 |
|
3 |
Rima’a |
2757 |
86 |
|
Canal Group |
Existing water rights (Service period) |
|
I |
From 19 Oct to 2 Aug |
|
II |
From 3 Aug to 13 Sept |
|
III |
From 14 Sept to 18 Oct |
Table 1.3: Wadi Zabid canals, Capacities,
Lengths and Irrigated Area
|
Canal Group |
Diversion structure no. |
Canal |
Bank |
Capacity |
Length km |
Gross irrigated area
ha |
Net irrigated area ha |
|
I |
1 |
Rodah |
Left |
2.5 |
2.3 |
30 |
25 |
|
I |
1 |
Bunav |
Right |
8.65 |
9.8 |
950 |
855 |
|
I |
1 |
Barv |
Right |
2.35 |
2.2 |
300 |
270 |
|
I |
1 |
Gerbah |
Left |
2.5 |
3.4 |
600 |
540 |
|
I |
2 |
Mansury |
Right |
15.0 |
10.4 |
1200 |
1080 |
|
I |
2 |
Ravvan |
Right |
15.0 |
13.5 |
1250 |
1125 |
|
I |
2 |
Bagr |
Right |
10.5 |
7.6 |
475 |
430 |
|
II |
3 |
Mawi |
Right |
30.0 |
14.7 |
2400 |
4325 |
|
II |
3 |
Ebri |
Left |
20.0 |
5.6 |
900 |
810 |
|
II |
3 |
Yusfi |
Right |
30.0 |
10.1 |
1275 |
1150 |
|
II |
3 |
Gerhazi |
Left |
20.0 |
9.8 |
1200 |
1080 |
|
II |
4 |
Gereb |
Center |
2.5 |
3.4 |
275 |
250 |
|
II |
4 |
Bira |
Left |
40.0 |
10.4 |
1475 |
1330 |
|
II |
4 |
Nasery |
Right |
---- |
---- |
2650 |
2385 |
|
III |
5 |
Sharabi |
Right |
20.0 |
7.3 |
625 |
560 |
|
III |
5 |
Maharaqi |
Left |
10.0 |
6.6 |
300 |
270 |
|
III |
5 |
Hrama |
Left |
10.0 |
5.8 |
250 |
225 |
|
III |
|
Wadi Ain |
---- |
---- |
275 |
250 |
|
|
Wadi Bed |
--- |
---- |
---- |
---- |
470 |
420 |
|
|
Totals |
238.5 |
122.9 |
16900 |
15216 |
|||
|
Reach (km) |
Design slope (m/m) |
1981 survey (m/m) |
1982 survey (m/m) |
1983 survey (m/m) |
1987 survey (m/m) |
1996 present survey (m/m) |
Ratio of (1996/design) |
|
A: Bunnay-Buarry canal |
|||||||
|
0 – 0.6 |
0.001 |
0.0012 |
0.002 |
0.0026 |
0.0022 |
0.0026 |
2.6 |
|
0.6-1.25 |
0.001 |
0.0016 |
0.0019 |
0.002 |
0.0014 |
0.0018 |
1.8 |
|
1.25-2.0 |
0.001 |
0.0015 |
0.0014 |
0.0021 |
0.0015 |
0.0013 |
1.3 |
|
2.0-2.15 |
0.001 |
0.0064 |
----- |
---- |
0.0012 |
0.0016 |
1.6 |
|
2.15-2.5 |
0.001 |
0.0016 |
----- |
---- |
0.0015 |
0.0021 |
2.1 |
|
B: Mawi-Yusifi canal |
|||||||
|
Reach (km) |
Built slope (m/m) |
1993 survey (m/m) |
Present 1996 survey (m/m) |
Ratio of (1996/as built) |
|
|
|
|
0 - 0.429 |
0.003 |
0.0017 |
0.0027 |
9 |
|
|
|
|
0.429-0.8 |
0.003 |
0.0026 |
0.0041 |
13.67 |
|
|
|
|
0.8-1.58 |
0.003 |
0.0015 |
0.0021 |
7 |
|
|
|
|
1.58 - 2.1 |
0.003 |
0.0008 |
0.0018 |
6 |
|
|
|
|
|
|